The enhancements released in Version 2.04 allow users involved in project management to maintain the following categories of project information:
Budget
Cash flow
Target dates
Planned employment generation
Actual employment generation
Planned socio economic impact
Actual socio economic impact
The maintenance functionality only becomes available after a baseline has been set by registering an appropriate form. For example, once a cash flow baseline has been set by registering a MIG 4 form, the cash flow can be maintained without the need to register MIG 6 or 8 forms. MIG 6 and 8 forms are of course still required as requests for payment, but not to update the cash flow or target dates. The cash flow sections have consequently been disabled on all forms except MIG 4 and target dates have been disabled on all forms except MIG 1.
All changes to project information made through project maintenance screens are recorded in a comprehensive audit trail.
Other enhancements include project suspension, project termination and site visit reports.